Inspection #15 - TopGolf - 2025-10-23
Equipment
-
Main Switchgear Panel A
Mechanical Room 1, Phoenix
- -
Main Switchgear Panel B
Mechanical Room 2, Phoenix
- -
Lighting Distribution Panel 1
Hallway A, Phoenix
- -
Lighting Distribution Panel 2
Hallway B, Phoenix
- -
Motor Control Center 1
Boiler Room, Phoenix
- -
Motor Control Center 2
Compressor Room, Phoenix
- -
HVAC Air Handler Unit 1
Roof Deck East, Phoenix
- -
HVAC Air Handler Unit 2
Roof Deck West, Phoenix
- -
Main Transformer T1
Outside North Pad, Phoenix
- -
Main Transformer T2
Outside South Pad, Phoenix
- -
Breaker Panel L1
Warehouse Wall A, Phoenix
- -
Breaker Panel L2
Warehouse Wall B, Phoenix
- -
Condenser Unit C1
Roof Zone A, Phoenix
- -
Condenser Unit C2
Roof Zone B, Phoenix
- -
Main Pump P1
Basement Pump Room, Phoenix
- -
Main Pump P2
Basement Pump Room, Phoenix
- -
Server Rack Power Strip 1
Data Room A, Phoenix
- -
Server Rack Power Strip 2
Data Room B, Phoenix
- -
Elevator Control Panel
Elevator Shaft Room, Phoenix
- -
Fire Pump Controller
Fire Control Room, Phoenix
-
Technicians
-
Peter Griffin
-
Tobias Funke
-
Micah Ray