Inspection #16 - TopGolf - 2025-10-23
Equipment
-
Main Switchgear Panel A
Mechanical Room 1, Miami
- -
Main Switchgear Panel B
Mechanical Room 2, Miami
- -
Lighting Distribution Panel 1
Hallway A, Miami
- -
Lighting Distribution Panel 2
Hallway B, Miami
- -
Motor Control Center 1
Boiler Room, Miami
- -
Motor Control Center 2
Compressor Room, Miami
- -
HVAC Air Handler Unit 1
Roof Deck East, Miami
- -
HVAC Air Handler Unit 2
Roof Deck West, Miami
- -
Main Transformer T1
Outside North Pad, Miami
- -
Main Transformer T2
Outside South Pad, Miami
- -
Breaker Panel L1
Warehouse Wall A, Miami
- -
Breaker Panel L2
Warehouse Wall B, Miami
- -
Condenser Unit C1
Roof Zone A, Miami
- -
Condenser Unit C2
Roof Zone B, Miami
- -
Main Pump P1
Basement Pump Room, Miami
- -
Main Pump P2
Basement Pump Room, Miami
- -
Server Rack Power Strip 1
Data Room A, Miami
- -
Server Rack Power Strip 2
Data Room B, Miami
- -
Elevator Control Panel
Elevator Shaft Room, Miami
- -
Fire Pump Controller
Fire Control Room, Miami
-
Technicians
-
Brian Wigginton
-
Homer Simpson
-
Peter Griffin